Microsoft Project accrues per-use costs at the start of a task. Let’s use the following resources to dig a little deeper: General Labourer – $14 / hour Supervisor – $50,000 / year Electrical Contractor – $5,000 cost / use First, I’ll create the resource list. Notice that all resources are configured to accrue costs on [...]
Archive for April, 2011
Per-Use Costs in Microsoft Project 2010